Lower Nazareth Elementary School - February & March Monthly Report

Work Ongoing - February

Work Ongoing - February

• Submittal processing. • Steel Wall angle bracing in Classroom addition. • Coordination and placement of roof curbs.

• Start installation of built-up roof insulation and roofing. • Interior framing of toilet rooms in Classroom addition. • Coordination with PPL for switch out of service with respect to new Transformer location. • Ongoing third-party inspections. • Ongoing plumbing inspections. • Ongoing Electrical CMUWall rough-in. • Coordination of Pressure grouting sink hole area. • Installation of feeder conduits towards new panels in Classroom addition. • Coordination with Switchgear change-out.

• Coordination with new transformer installation. • Roofing of Classroom addition and Admin addition.