Lower Nazareth Elementary School - February & March Monthly Report

Report Submission Date:

03/31/21

Report Author: Lee Werkheiser

2021

2022

Status Comments

M ‐ J J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J J ‐ A S ‐ O N ‐ D

% Complete

100% Phase 1 site work has been completed

100% Phase 1 building demolition, CMU, Foundations, Concrete floor has been completed. Structural steel complete. Load bearing CMU wall installation is Complete. Roof decking is complete. 97% Above Ceiling HVAC ducts installed. Above ceiling MC, FA, data cable and junction boxes installed. Casework in classrooms. Painted. Ceiling grid. 51%

0%

Phase 2 addition is ongoing, structural steel is complete, Demolition of existing stage is complete. Underslab plumbing is complete. Slab is placed at addition and at interior of old Stage area. Stud framing has commenced. Joist installation complete.

64%

0%

0%

0%

0%

Phase 1 2021

Status Comments

M A M J J A S O N D

% Complete

97% Installation of door frames and interior CMU walls. 2 HR separation walls framed, Fire proofing completed on Door structural frame. Generator slab poured. Electrical panels installed Overhead MEP work commenced. Completed exterior CMU walls. Installed Steel wall angle framing. Installed exterior door frame. Concrete foundation and slab complete. Fire walls complete. Metal frame parapet walls complete. 51% Roof top equipment placed, interior painting continuing, casework being placed

61%

Issues in Progress Smaller sinkhole pressure grouting at West Elevation after snow melts

ate (with 10% tained)

Original Material Allowance

Remaining Material Allowance

Executed Change Orders

$ $ $ $ $ $

316,308 53,746 42,088 38,639

2,229,436

$ $ $ $ $ $

‐ ‐ ‐ ‐ ‐ ‐

$ $ $ $ $ $

348,915 56,150 60,350 42,270

513,895 431,558 252,050

2,934

2,273

2,934

453,715

3,429,212

510,619