Lower Nazareth Elementary School
Animated publication
Construction Manager
Lower Nazareth Elementary School Nazareth Area School District
DEI Project No.017169 Monthly Progress Report No.02 November 2020
Work Completed
•Start: July 15, 2020 •Completion of Phase: April 5, 2021 Phase B1.1-B1.30: Building Phase 1
• Classroom CMU foundations and flashings completed at Classroom addition • Under slab MEP installation • EC and PC under slab inspections • Stone installation and compaction for slab in Classroom and Administration areas • Interior perimeter insulation installed • Slab prep and poured in Classroom and slab prep at Administration addition • Interior Group toilet room CMU completed • Exterior Inlet and piping placed on East side of Classroom addition • Structural steel erected at Administration addition • Demolition of existing wall for new opening for Administration area future doorway Work COmpleted
Administration Area Slab Preparation
Administration Area Steel Erection
NOvember 2020
Work Ongoing
Work Ongoing
• Submittal processing • Coordination Drawings • Installation of CMU steel bearing walls • Export of fill
• Coordination for generator relocation and conduit runs • Coordination for relocation of transformer location • Coordination of off-site inspections of steel, at fabricator shop
• Ongoing third-party inspections • Ongoing plumbing inspections • Ongoing electrical rough-in • Coordination with new electrical service • CMU interior wall layouts
• Interior door frame installations • Demo work at existing stage area
Concrete Slab Preparation
CMU Exterior Wall Placement
Concrete Slab Pour
In Wall MEP Rough-in
Interior CMUWalls
Interior Corridor CMU Placement
November 2020
Work Ongoing
New Administration Door Opening
Perimeter CMUWalls
Setting Door Frames
Stage Demolition
Steel Decking Delivery
Steel Joist Delivery
Vapor Barrier Installation
Overall Site Photo
November 2020
Building Layout
November 2020
School District: Nazareth Area School District Project Name: Lower Nazareth Elementary School Additions & Renovations Project Number: 017169
2020
Overall Project Schedule Status
J‐F M‐A M‐J J‐A S‐O N‐D J‐F M‐A M
Site Phase 1 S1.1 ‐ S1.12 Temp E&S, const. entr.,utility disconnect,new water line,new ductbank,rem. grease trap,strip topsoil,inst. Basin & storm water syst.,prep building addition pad Bldg. Phase B1.1‐B1.5 Bldg protection, disconnect bldg systems in spaces demolished, selective demo, inst. New utilities, new conc floor, add't foundation, CMU for slab install B1.6‐B1.14 Under slab utilities, slab‐on‐grade, load bearing CMU, roof steel, interior CMU partitions, tie‐in roof B1.15‐1.22‐ Inst. MEP system equip & inspections, wall finishes and casework,ceiling grid,ceiling mounted devices/fixtures,inspections,inst. flooring B1.23‐1.30 ‐ Permanent power, equip. start‐up & commissioning mech. equip., equip. start‐up & commissioning elect., plumb, GC systems, move In B2.1‐B2.14‐Inter. Bldg. protection,select demo,inst. Add'n. Found/CMU, undersla elect,mech,plumbing,struct steel for add'n, conc. slab on grade, fire wall,ext. shell,int. walls,roof top equip,int. CMU walls B2.15‐B2.25 ‐ Inst. rooftop equip, roof tie‐ins, rem. temp. partitions,above ceiling mech, elect, plumb and inspections,wall finish and casework,ceiling grid,ceiling mounted devices/fixtures and inspections,inst.flooring B2.26‐B2.33 ‐ Rem. partition, equip. start‐up & commissioning of elect., plumb & GC systems, sub. comp. and move‐in to admin addition B3.1‐B3.14 ‐ Abate caf and lobby,select demo, int. walls,roof top and above ceiling mech, elect, plumb systems and inspections, int. walls finish and casework, above ceiling mounted devices/fixtures and inspections,inst. flooring,sub. completion, final completion Site Phase 2.1‐2.7 Inst E&S, patch conc. Sidewalks, final grade & landscaping,rem const trailer/staging, inst. New basketball court
Building
Current Phase and Schedule Status
J A S O N D J F
B1.6‐B1.10 Install underslab electrical, mechanical & plumbing syst. CMU framing for addition, roof steel, roof deck,concrete slab on grade B2.1‐B2.14: Installation of strutural steel, Slab on Grade and CMU walls
Issues Resolved
$ $ $ $ $ $ Paid to D re
42,082 $ 7,146,680 $ 456,001 $ 1,287,597 $ 939,000 $ 4,422,000 $ Contract Amount
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: JBM Mechanical, Inc. Environmental Contractor: PRISM Response, LLC
Total
Report Submission Date:
11/01/20
Report Author: Lee Werkheiser
2021
2022
Status Comments
% Complete
M‐J J‐A S‐O N‐D J‐F M‐A M‐J J‐A S‐O N‐D
100% Phase 1 site work has been completed
100% Phase 1 Building addition has been completed
Under slab utilities and slab on grade complete. Load bearing CMU wall installation is ongoing
25%
0%
0%
Phase 2 aadition has begun, structural steel is placed, Demolition of existing stage has begun.
43%
0%
0%
0%
0%
g Phase 1 2020
Status Comments
M A M J J A S O N D
% Complete
TV, Data, outlet and camera location coordination with District 2 sink holes being looked into on West and North sides of Classroom addition Issues in Progress
Remaining Material Allowance
Date (with 10% etained)
2,934 $ 515,354 $ 42,270 $ 70,490 $ 43,280 $ 356,380 $ Original Material Allowance
‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ Executed Change Orders
118,302 155,192 90,364 1,175,486
356,380 $ 43,280 $ 70,490 $ 42,270 $ 2,934 $ 515,354 $
2,273
1,541,616
Printed 12/10/2020 1 of 2
Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal
School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts
Construction Manager D’Huy Engineering, Inc.
Project Architect Alloy5 Architecture
Contractors CMG of Easton, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Wind Gap Electric, Inc. Electrical Construction
JBMMechanical, Inc. Plumbing Construction
Made with FlippingBook Ebook Creator