Work Completed
•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition
Work Completed
• Gym joist and decking installed • Basin #2 amended soils tested • Coordination drawings • Procurement of roofing materials to site • Structural steel framing of Gym and Storage area • Installation of roof curbs on Nurse’s addition • Procurement of roof drains and installation on Nurse’s addition
and Classroom addition areas • Roof installation at Nurse’s addition
Door Frame Installation
Roofing Material
2 Hour Fire Wall Installation
January 2021
Work Ongoing
• Submittal processing • In wall electrical rough-in • In stone electrical rough-in at Gym • Coordination of porous paving at new parking area • Coordination with District on construction related items that may affect traffic • Coordination of EC switchgear panel installation • Coordination and installation of MEP in-wall rough ins • Installation of door frames in Classroom addition • Interior Classroom CMU walls • Exterior Gym CMU walls • Sheathing parapet walls on Classroom addition • Framing parapet walls on Gym • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping • Placement of roof curbs for RTU units and exhaust fans on Classroom addition • Procurement of brick • Installation of duct work in Classroom and Nurse’s addition • Installation of above ceiling MEP rough in • Ongoing L&I inspections of framing and plumbing rough in • Ongoing DBA inspections for CMU grout, mortar and compaction testing Work Ongoing
Installation of Roof Drains
Installation of Parapet Walls
Above Ceiling MEP Installation
January 2021
Work Ongoing
Interior CMUWall Installation
Nurse’s Suite Rough Framing
Interior Classroom CMU
Installation of Roof Leaders
North Side of Gym CMU Installation
Nurse’s Addition Roof Installation
January 2021
Work Ongoing
Nurse’s Suite Rough Wiring
Procurement of Roofing Material
Roof Drain Installation
Setting Structural Steel in Gym
Spray Foam Vapor Barrier
January 2021
Building Layout
Drone Photo of Classroom Addition
January 2021
School District: Nazareth Area School District Project Name: Kenneth N. Butz, Jr. Elementary School Addition & Renovations Project Number: 017170
2020
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O
Site Phasing Phase 1 ‐ S1.0 ‐ S1.7 ‐ Temp E&S, Staging Area, Const Entrance, Temp Power, site lighting, strip topsoil, relocate elect and water to pavilion, inst Basin 002 and storm water system.
Building Phase 1 ‐ B1.0 ‐ B1.12 ‐ Existing building protective measures, Disconnect MEP for Gym Demo, Gym demo, Sanitary Demo and pour slab at Vest., Below grade foundation demo, Pad prep., Install footing and foundations, Install underslab MEP work, Erect structural steel, Install metal roof deck and roofing, Concrete slab on grade, Fire Wall Building Phase 1 ‐ B1.13 ‐ B1.19 ‐ Const ext. shell & int. CMU walls, inst rooftop equip., final roof tie ‐ ins to new & exist systems, inst mech, elect, plumbing wall mounted equip & inspections. Building Phase 1 ‐ B1.20 ‐ B1.33 ‐ Inst terrazzo flr., inst. Wall finish, casework, ceiling grid, ceiling mounted devices & fixtures, above ceiling inspections, inst. Flooring, energize perm power, equip. start ‐ up & commissioning of mech, elect, plumb & GC systems, bldg substantial completion. Building Phase 2 ‐ B2.0 ‐ 2.10 ‐ Inst int. protective measure for bldg. demo, selective demo, bldg. add'n pad & CMU for slab inst., inst. underslab elect, mech, plumb syst., erect struct. steel, metal roof deck & roofing, inst. Concrete slab on grade, const ext shell. Building Phase 2 ‐ B2.11 ‐ B2.21 ‐ Const. int. walls, inst. rooftop equip., final roof tie ‐ ins, inst. above ceiling mech, elect, plumb and wall mounted mech, elect, plumb and inspections, inst. wall finish & casework & ceiling grid, inst. ceiling mounted devices & fixtures, above ceiling inspections, inst. flooring. Building Phase 2 ‐ B2.22 ‐ B2.34 ‐ Energize perm. Power, rem int. temp partition, abatement & sel demo and in lobby and admin areas, const int. walls lobby and admin area, inst above ceiling mech, elect, plumb systems and inspections, inst. Wall mounted mech, elect, plumb equip and inspections, inst wall finish, casework, ceiling grid, inst ceiling mounted devices & fixtures and above ceiling inspections, inst flooring. Building Phase 2 ‐ B2.35 ‐ B2.37 Final Inspections, Substantial Completion & Final Completion Site Phasing Phase 2 ‐ S2.0 ‐ S2.7 ‐ Relocate const fence, temp E&S, patch concrete sidewalks, final grading & landscaping, remove const trailers, new basketball court & repair paving
Current Phase and Schedule Status ‐ Site Phase 1, Building Phase 1 & Building Phase 2
J
A S O N
S1.0 ‐ S1.7: Basin 1 finished, Basin 2 beginning, soil export complete.
B1.0 ‐ B1.12: Structural Steel and Joist installation B2.0 ‐ 2.10: Structural Steel placement, CMU wall construction S2.0 ‐ S2.7: Site work related to Nurse's Suite addition & additional parking has started
Issues Resolved Amended soils for basin 002 tested for percolation rates
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: PRISM Response LLC
Contract Amount
$ $ $ $ $ $
4,779,250
764,000
1,069,885
317,000 92,228
7,022,363
Total
Report Submission Date:
January 2021
Report Author:
Lee Werkheiser
2021
2022
Status Comments
O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D
% Complete
NTP issued, Shop dwgs, long lead items submitted, Temp E&S inst, Project trailers, power comp, Staging area comp, site cleared, strip topsoil comp, relocated power & water to pavilion, new fire hydrant & water line comp, Basin 002 excavated. Existing Gym Demo, MEP utilities capped. Sanitary line inst, bldg add footings, piers & foundations inst. Underground MEP work, slab on grade comp except Gym area. Structural steel, roof deck inst above classrooms. Completed structural steel & decking. Coordination drawings completed. Roof top equipment delivered to site. Roof top curbs installed on deck of classroom addition. Coordination with slab saw cuts with Terrazzo complete. Work on Phase 2 (Nurse's Suite Addition) began early. Demo of exterior PTA room wall complete. Under slab utilities & foundations comp. Slab on grade complete. Structural steel & Roof deck comp. CMU walls completed. Fire wall completed. Metal studs commenced. ductwork installed.
90%
81%
36%
0%
94%
0%
0%
0%
E&S installed, Installed Basin 001, Poured curb and sidewalks, installed stone at new parking areas, installed berm with fill material and placed topsoil. Hydro seeded berm.
33%
Phase 1 2020
Status Comments
D J
F M A M J
J
A S O N D
% Complete
Basin 2 installation is beginning Steel is complete, CMU walls is ongoing. Above ceiling MEP work continuing.
Started Nurse's Suite early. Steel & CMU walls complete.
Paving is wrapping up at new parking spaces
Issues in Progress
Remaining Material Allowance
Original Material Allowance
Paid to Date (with 10% retained)
Executed Change Orders
0 0 5 0 8 3
$ $ $ $ $ $
2,188,395
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
360,745 43,330 60,350 43,756
$ $ $ $ $ $
360,745 43,330 55,662 43,756
244,625 159,886 151,682
‐
7,620
2,934
503,493
2,752,209
511,115
Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal
School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts
Construction Manager D’Huy Engineering, Inc.
Project Architect Alloy5 Architecture
Contractors CMG of Easton, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Wind Gap Electric, Inc. Electrical Construction
JBMMechanical, Inc. Plumbing Construction