Work Ongoing - February
Work Ongoing - February
• Submittal processing. • InWall Electrical Rough-in at Gym. • In Stone Electrical Rough-in at Gym. • Coordination of Porous Paving at new parking area. • Coordination with district on construction related items that may affect traffic. • Coordination of EC switchgear panel installation. • Coordination and installation of MEP in-wall rough ins. • Interior CMU walls in Gym addition. • Roof curb layout on Classroom and Gym roof. • Exterior Gym CMU walls. • Framing and sheathing parapet walls on Gym. • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping. • Placement of roof curbs for RTU units and exhaust fans on Classroom addition. • Procurement of Brick. • Installation of above ceiling MEP rough in. • Ongoing L&I inspections of framing and plumbing rough-in. • Ongoing DBA inspections for CMU grout, mortar and compaction testing.
Installation of CMU at Group Toilets
Air Barrier Applied in Gym CMU
Made with FlippingBook Learn more on our blog