Kenneth N. Butz, Jr. Elementary School - February & March Monthly Report
Work Completed - February
•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition
Work Completed - February
• Tenting in Gym and completing Gym perimeter wall CMU. • Brick installation of Nurses addition. • Ductwork and VAV installation in Classroom and Nurse additions. • Interior steel wall angle supports in Classroom addition. • Installation of metal frame Parapet walls on Classroom addition. • Installation of electrical panels in Electrical room. • Installation of exterior door frames at Gym addition. • Installation of interior Classroom door frames. • Procurement and Coordination of Gym Ductwork. • Installation of spray foam vapor barrier to Classroom addition. • Domestic water piping inspection.
• Installation of electrical panels in Basement. • In wall electrical rough-in at Classroom addition.
• Nurse’s addition spray fire proofing. • Metal framing in Nurse addition.