Kenneth N. Butz, Jr. Elementary School - February & March Monthly Report

Work Ongoing - march

• Submittal processing. • Above Electrical Rough-in at Gym. • Coordination of Porous Paving at new parking area. • Coordination with district on construction related items that may affect traffic. • Coordination of EC switchgear panel installation. • Roof curb layout on Classroom addition. • Exterior Classroom Brick Veneer installation. • Placement of roof curbs for RTU units and exhaust fans on Classroom addition. • Installation of above ceiling MEP rough in. • Ongoing L&I inspections of framing and plumbing rough-in. • Ongoing DBA inspections for CMU grout, mortar and compaction testing. Work Ongoing - March

Gym Slab Vapor Barrier Installation

Gym Addition Masonry Work

Framing at Gym Lobby

Gym Entrance Framing Installation