Kenneth N. Butz, Jr. Elementary School - February & March Monthly Report
Animated publication
Construction Manager
KENNETH N. BUTZ, JR. ELEMENTARY SCHOOL Nazareth Area School District
DEI Project No.017170 Monthly Progress Report No.5-6 February & March 2021
Work Completed - February
•Start: August 15, 2020 •Completion of Phase: April 9, 2021 Phase 1: Classroom/Gymnasium Building Addition
Work Completed - February
• Tenting in Gym and completing Gym perimeter wall CMU. • Brick installation of Nurses addition. • Ductwork and VAV installation in Classroom and Nurse additions. • Interior steel wall angle supports in Classroom addition. • Installation of metal frame Parapet walls on Classroom addition. • Installation of electrical panels in Electrical room. • Installation of exterior door frames at Gym addition. • Installation of interior Classroom door frames. • Procurement and Coordination of Gym Ductwork. • Installation of spray foam vapor barrier to Classroom addition. • Domestic water piping inspection.
• Installation of electrical panels in Basement. • In wall electrical rough-in at Classroom addition.
• Nurse’s addition spray fire proofing. • Metal framing in Nurse addition.
2-Hour Fireproofing Spray at Nurse’s Addition
Above Ceiling MEP Rough-In
February & March 2021
Work Ongoing - February
Work Ongoing - February
• Submittal processing. • InWall Electrical Rough-in at Gym. • In Stone Electrical Rough-in at Gym. • Coordination of Porous Paving at new parking area. • Coordination with district on construction related items that may affect traffic. • Coordination of EC switchgear panel installation. • Coordination and installation of MEP in-wall rough ins. • Interior CMU walls in Gym addition. • Roof curb layout on Classroom and Gym roof. • Exterior Gym CMU walls. • Framing and sheathing parapet walls on Gym. • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping. • Placement of roof curbs for RTU units and exhaust fans on Classroom addition. • Procurement of Brick. • Installation of above ceiling MEP rough in. • Ongoing L&I inspections of framing and plumbing rough-in. • Ongoing DBA inspections for CMU grout, mortar and compaction testing.
Installation of CMU at Group Toilets
Air Barrier Applied in Gym CMU
Framing of Parapet Walls
Gym CMUWalls
February & March 2021
Work Ongoing - February
Installation of VAVs and Ductwork
Interior CMU at Classroom Addition
In-Wall Electrical Rough-in
Steel Bridging Installation
Nurse’s Addition Air Barrier Installation
Ongoing Gym CMUWalls
February & March 2021
Work Completed - March
Work Completed - March
• Installation of Roof drain piping in Classroom addition. • Installation of interior walls and frames in Gym addition. • Prep and pour Gym floor concrete slab. • Excavated, ran conduits and poured Generator pad. • Framed Parapet walls on Gym addition. • Basin #2 inspection of percolation of bottom of basin, prior to installing stone and piping. • Basin 2 installation. • Installation of inlets on North side of Classroom addition to Basin 2. • Installed Domestic Water Piping through Gym to Toilet room.
• Interior steel wall angle supports in Gym addition. • Installation of roof curbs on Gym roof addition. • Installation of built up roof insulation and watertight on Gym roof. • Installation of spray foam vapor barrier to Gym addition. • Delivery of Generator and placed on pad.
CMUWraps in Classroom Addition
Excavate and Place a New Generator Pad
Brick Veneer Installation on Nurse’s Addition
Completion of Perimeter CMU
February & March 2021
Work Ongoing - march
• Submittal processing. • Above Electrical Rough-in at Gym. • Coordination of Porous Paving at new parking area. • Coordination with district on construction related items that may affect traffic. • Coordination of EC switchgear panel installation. • Roof curb layout on Classroom addition. • Exterior Classroom Brick Veneer installation. • Placement of roof curbs for RTU units and exhaust fans on Classroom addition. • Installation of above ceiling MEP rough in. • Ongoing L&I inspections of framing and plumbing rough-in. • Ongoing DBA inspections for CMU grout, mortar and compaction testing. Work Ongoing - March
Gym Slab Vapor Barrier Installation
Gym Addition Masonry Work
Framing at Gym Lobby
Gym Entrance Framing Installation
Installation of Brick Veneer
Installation of Gym Ductwork
Installation of Domestic Water Line
Installation of Moveable Partition Track
Installation of Cable Tray
Installation of Nurse’s Addition Roof
February & March 2021
Work Ongoing
Installation of Parapet Wall Framing
Interior CMU at Group Toilet Rooms
Installation of Stone in Basin 2
North Side Site Inlet Installation
Poured Gym Slab
Tenting Gym to AllowMasonry Work to Proceed from Inside Tent
February & March 2021
Building Layout
Drone Photo of Classroom Addition
February & March 2021
School District: Nazareth Area School District Project Name: Kenneth N. Butz, Jr. Elementary School Addition & Renovations Project Number: 017170
2020
Overall Project Schedule Status
J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A
Site Phasing Phase 1 ‐ S1.0 ‐ S1.7 ‐ Temp E&S, Staging Area, Const Entrance, Temp Power, site lighting, strip topsoil, relocate elect and water to pavilion, inst Basin 002 and storm water system. Building Phase 1 ‐ B1.0 ‐ B1.12 ‐ Existing building protective measures, Disconnect MEP for Gym Demo, Gym demo, Sanitary Demo and pour slab at Vest., Below grade foundation demo, Pad prep., Install footing and foundations, Install underslab MEP work, Erect structural steel, Install metal roof deck and roofing, Concrete slab on grade, Fire Wall Building Phase 1 ‐ B1.13 ‐ B1.19 ‐ Const ext. shell & int. CMU walls, inst rooftop equip., final roof tie ‐ ins to new & exist systems, inst mech, elect, plumbing wall mounted equip & inspections. Building Phase 1 ‐ B1.20 ‐ B1.33 ‐ Inst terrazzo flr., inst. Wall finish, casework, ceiling grid, ceiling mounted devices & fixtures, above ceiling inspections, inst. Flooring, energize perm power, equip. start ‐ up & commissioning of mech, elect, plumb & GC systems, bldg substantial completion. Building Phase 2 ‐ B2.0 ‐ 2.10 ‐ Inst int. protective measure for bldg. demo, selective demo, bldg. add'n pad & CMU for slab inst., inst. underslab elect, mech, plumb syst., erect struct. steel, metal roof deck & roofing, inst. Concrete slab on grade, const ext shell. Building Phase 2 ‐ B2.11 ‐ B2.21 ‐ Const. int. walls, inst. rooftop equip., final roof tie ‐ ins, inst. above ceiling mech, elect, plumb and wall mounted mech, elect, plumb and inspections, inst. wall finish & casework & ceiling grid, inst. ceiling mounted devices & fixtures, above ceiling inspections, inst. flooring. Building Phase 2 ‐ B2.22 ‐ B2.34 ‐ Energize perm. Power, rem int. temp partition, abatement & sel demo and in lobby and admin areas, const int. walls lobby and admin area, inst above ceiling mech, elect, plumb systems and inspections, inst. Wall mounted mech, elect, plumb equip and inspections, inst wall finish, casework, ceiling grid, inst ceiling mounted devices & fixtures and above ceiling inspections, inst flooring. Building Phase 2 ‐ B2.35 ‐ B2.37 Final Inspections, Substantial Completion & Final Completion Site Phasing Phase 2 ‐ S2.0 ‐ S2.7 ‐ Relocate const fence, temp E&S, patch concrete sidewalks, final grading & landscaping, remove const trailers, new basketball court & repair paving Current Phase and Schedule Status ‐ Site Phase 1, Building Phase 1 & Building Phase 2
J
A S O N D J
F
S1.0 ‐ S1.7: Basin 1 finished, Basin 2 , soil export.
B1.0 ‐ B1.12: Structural Steel and Joist installation
B1.13 ‐ B1.19: Install MEP wall mounted equipment
B1.20 ‐ B1.33: Interior Finishes B2.0 ‐ 2.10: Structural Steel placement, CMU wall construction S2.0 ‐ S2.7: Site work related to Nurse's Suite addition & additional parking has started
Issues Resolved
Possible relocation of Conference Room Plan
Paid to D
Contract General Contractor: CMG of Easton, Inc. Mechanical Contractor: JBM Mechanical, Inc. Electrical Contractor: Wind Gap Electric, Inc. Plumbing Contractor: Myco Mechanical, Inc. Environmental Contractor: PRISM Response LLC
Contract Amount
$ $ $ $ $ $
4,779,250
$ $ $ $ $ $
764,000
1,069,885
317,000 92,228
Total
7,022,363
Report Submission Date:
March 2021
Report Author:
Lee Werkheiser
2021
2022
Status Comments
M ‐ J
J ‐ A S ‐ O N ‐ D J ‐ F M ‐ A M ‐ J
J ‐ A S ‐ O N ‐ D
% Complete
100% NTP issued, Shop dwgs, long lead items submitted, Temp E&S inst, Project trailers, power comp, Staging area comp, site cleared, strip topsoil comp, relocated power & water to pavilion, new fire hydrant & water line comp, Existing Gym Demo, MEP utilities capped. Sanitary line inst, bldg add footings, piers & foundations inst. Underground MEP work, slab on grade completed. Completed structural steel & decking. Above ceiling MEP installed. Roof drain piping installed. Interior cmu walls complete. 97% Coordination drawings completed. Roof top equipment delivered to site. Roof top curbs installed on deck of classroom addition.
58%
Coordination with slab saw cuts with Terrazzo complete.Casework on site. All doorframes installed.
5%
91% Work on Phase 2 (Nurse's Suite Addition) began early. Demo of exterior PTA room wall complete. Under slab utilities & foundations comp. Slab on grade complete. Structural steel & Roof deck comp. CMU walls completed. Fire wall completed. Metal studs and sheetrocked. ductwork started.Fire
0%
0%
0%
E&S installed, Installed Basin 001, Poured curb and sidewalks, installed stone at new parking areas, installed berm with fill material and placed topsoil. Hydro seeded berm.
34%
Phase 1 2020
Status Comments
M A M J
J
A S O N D
% Complete
100% Basin 2 installation is complete
100% Steel is complete, CMU interior and exterior walls are complete. All Slab on grade complete.
58% Roof top units set, preparing to install wall mounted fixtures.
5% Block filler is being installed, tile work to begin.
91% Started Nurse's Suite early. Steel & CMU walls complete.Fire wall complete. Metal framing complete.
34% Paving is wrapping up at new parking spaces. Curb and sidewalks completed. Inets installed.
Issues in Progress
Phase 2 removal of Site soils for completion. Admin time clock location on wall to be demo'd.
Original Material Allowance
Remaining Material Allowance
Date (with 10% retained)
Executed Change Orders
2,643,769
$ $ $ $ $ $
‐ ‐ ‐ ‐ ‐ ‐
$ $ $ $ $ $
60,350 43,756 56,200 347,745
$ $ $ $ $ $
237,774 56,200 55,662 43,756
343,036 196,280 416,787
7,620
2,934
‐
3,607,493
510,985
393,392
Dr. Dennis Riker, Superintendent Dr. Stuart Whiteleather, Business Administrator Mr. Robert Zemanick, Director of Facilities & Operations Mr.Michael Santos, Principal
School Board Dr. Linda Stubits, President Joseph Vasko, Vice President Kenneth N. Butz, Jr. Denise Glaros Melissa Kalinoski Gregory Leh Jodi Mammana Dr. AdamMcGlynn Kathryn Roberts
Construction Manager D’Huy Engineering, Inc.
Project Architect Alloy5 Architecture
Contractors CMG of Easton, Inc. General Construction
JBMMechanical, Inc. Mechanical Construction
Wind Gap Electric, Inc. Electrical Construction
JBMMechanical, Inc. Plumbing Construction