Improvement to Southern Lehigh Field Complex
PROJECT SCHEDULE
2022
2023
SOUTHERN LEHIGH STADIUM SCHEDULE
J J A S O N D J F M A M J J A S
School District obtain NPDES Permit School District obtain Twp land Development Approval School District submit construction documents for Twp Building Code Review and Permit Complete electrical design for Twp permit drawings School District complete Clean Fill Certification and direction Final agreement on detailed project cost and schedule Submit, review/approve shop drawings for sitework/stormwater w/Engineer Stormwater procurement Submit, review and approve track trench drain shop drawings and procurement Work with School District to complete home bleacher and pressbox package/purchase Home bleacher procurement and delivery Work with School District and Architect to select/purchase turf, colors and shock pad (TBD) Synthetic Turf procurement and delivery Work with School District to select scoreboard/audio system and authorize purchase Scoreboard procurement and delivery Work with School District to select stadium lighting and authorize purchase Stadium lighting procurement and delivery Work with School District to confirm/purchase track surface, lines and colors Track surfacing procurement and delivery Site survey, security erosion and sediment controls Site stadium demolition (track, field and bleachers) and stadium light poles if required Construct new stadium bleacher foundations Construct new stadium light pole bases if required Track grading and stormwater installation (as weather permits)
X:\SURVECADD\ARCHITERRA\SOUTH LEHIGH\SITEPLANS\REV 03-01-22\SP-08 AERIAL PHOTOGRAPHIC PLAN.dwg
Track trenchdrain installation Track asphalt subgrade prep Strip field for grading Construct scoreboard foundation and steel New light pole install (if needed)
Home bleacher and pressbox installation Field underdrains and drainage stone Site electrical installation including new conduit and wire across field for lights/power Install synthetic turf
Track asphalt paving and 30 day cure time Stadium lighting installation and testing New scoreboard installation Final electrical and data to pressbox Site fencing Urethane track systems install and line striping Conversion of stormwater to post construction Final landscaping
Made with FlippingBook - Online Brochure Maker