Construction Manager

CROOKED BILLET ELEMENTARY SCHOOL Hatboro-Horsham School District DEI Project No. 284003 Monthly Progress Report No. 17 February 2020

P a g e | 2

Crooked Billet Elementary School Hatboro-Horsham School District

Phase 2: Building Enclosure, Systems, and Finishes Notice to Proceed: August 20, 2018 Substantial Completion: June 19, 2020 Final Completion: July 9, 2020

MDF Room Racks and Cable Management

WORK COMPLETED − Drywall finishing and paint in Media Room − Drywall installed in first floor A Cafeteria and Corridors − Installation of roll up smoke shutter in Corridor − Installation of ceiling grid in Admin area − Second floor Terrazzo in Corridor − VCT tile installation in second floor classrooms − Ceramic tile installation on first and second floor classrooms and corridors − Ceramic tile installation in group toilet rooms − Installation of toilet room vents to all second floor toilet rooms − Aluminum storefront in Upper Media Room − Installation of lights and GRD’s in first and second floor classrooms − Installation of first floor casework in Admin, Art, and Music Rooms − Installation of whiteboards and tack boards in Admin, Art, and Music areas

Music Room Casework

Group Toilet Partitions

P a g e | 3

− Installation of elevator and chair lift − Installed sprinkler heads through ceiling on second floor

− Sprinkler mains in Kitchen − Installed lighting in Gym

− Electrical wiring to VAV’s in Boiler room − Installed Loading Dock leveler and bumpers − Installed roof on large canopy and by entrance Vestibule V103 − Domestic piping to water pumps − Closed water HVAC system chemical cleaning and flushing − Gas piping installation − Gas Pressure reducing valve installation and coordinated with PECO Gas meter installation and turn on

Loading Dock Leveler and Bumpers

Boiler Room Work

AHU ATC Wiring

Installation of PECO Gas Meter

P a g e | 4

WORK ONGOING − Skepton (GC) is providing temporary heat inside the building for all trades. − Area A painting continues. − First floor Terrazzo installation has begun. − Interior drywall finishing continues in Media Room. − Drywall installation to underside of deck at chair storage areas ongoing. − Installation of casework in Admin area is ongoing. − Ongoing installation of folding partitions in classrooms. − Piping insulation in Area A continues. − Mechanical, electrical, and plumbing above ceiling rough-in continues in Area A. − Sprinkler branch lines continuing in Area A. − VAV units and terminal units continue to be installed in Area A. − Area A ductwork continues. − HVAC control wiring installation ongoing. − Mechanical Mezzanine HVAC control wiring ongoing. − Circuits being pulled to electrical panels in Area A. − Fire alarm wiring installation ongoing in area A. − Data, fire alarm, and security wiring being pulled continues. − Window and curtain wall installation continues. − Domestic water piping installation to water heaters ongoing.

First Floor Terrazzo Finishing

Mechanical Mezzanine Control Panels

Piping Water Heaters

P a g e | 5

− Roof soffit and fascia installation continues. − Fascia gutter and downspout installation ongoing.

Mechanical Mezzanine

Installation of Wet Bed in Kitchen

Boiler Start Up

Quarry Tile Installation in Kitchen

Area C Mezzanine Ductwork

P a g e | 6

Building Feature Highlight The Crooked Billet site slopes from front to back. To take advantage of the topography and in lieu of adding more stone fill on the site, a District-wide storage room was incorporated into the school design. The space can be accessed

from both inside and out and is equipped with fire suppression, security, and data systems. CROOKED BILLET ELEMENTARY

Gym Floor Prep for Wood Flooring

Gym Scoreboard Placement

P a g e | 7

SGA Rendering of Area A

2/29/20 Status of Area A

P a g e | 8

Aerial view of Site

Aerial view of Area B and C

P a g e | 9

Building Layout:

AREA C

AREA A

AREA B