CROOKED BILLET ELEMENTARY SCHOOL
Animated publication
Construction Manager
CROOKED BILLET ELEMENTARY SCHOOL Hatboro-Horsham School District DEI Project No. 284003 Monthly Progress Report No. 17 February 2020
P a g e | 2
Crooked Billet Elementary School Hatboro-Horsham School District
Phase 2: Building Enclosure, Systems, and Finishes Notice to Proceed: August 20, 2018 Substantial Completion: June 19, 2020 Final Completion: July 9, 2020
MDF Room Racks and Cable Management
WORK COMPLETED − Drywall finishing and paint in Media Room − Drywall installed in first floor A Cafeteria and Corridors − Installation of roll up smoke shutter in Corridor − Installation of ceiling grid in Admin area − Second floor Terrazzo in Corridor − VCT tile installation in second floor classrooms − Ceramic tile installation on first and second floor classrooms and corridors − Ceramic tile installation in group toilet rooms − Installation of toilet room vents to all second floor toilet rooms − Aluminum storefront in Upper Media Room − Installation of lights and GRD’s in first and second floor classrooms − Installation of first floor casework in Admin, Art, and Music Rooms − Installation of whiteboards and tack boards in Admin, Art, and Music areas
Music Room Casework
Group Toilet Partitions
P a g e | 3
− Installation of elevator and chair lift − Installed sprinkler heads through ceiling on second floor
− Sprinkler mains in Kitchen − Installed lighting in Gym
− Electrical wiring to VAV’s in Boiler room − Installed Loading Dock leveler and bumpers − Installed roof on large canopy and by entrance Vestibule V103 − Domestic piping to water pumps − Closed water HVAC system chemical cleaning and flushing − Gas piping installation − Gas Pressure reducing valve installation and coordinated with PECO Gas meter installation and turn on
Loading Dock Leveler and Bumpers
Boiler Room Work
AHU ATC Wiring
Installation of PECO Gas Meter
P a g e | 4
WORK ONGOING − Skepton (GC) is providing temporary heat inside the building for all trades. − Area A painting continues. − First floor Terrazzo installation has begun. − Interior drywall finishing continues in Media Room. − Drywall installation to underside of deck at chair storage areas ongoing. − Installation of casework in Admin area is ongoing. − Ongoing installation of folding partitions in classrooms. − Piping insulation in Area A continues. − Mechanical, electrical, and plumbing above ceiling rough-in continues in Area A. − Sprinkler branch lines continuing in Area A. − VAV units and terminal units continue to be installed in Area A. − Area A ductwork continues. − HVAC control wiring installation ongoing. − Mechanical Mezzanine HVAC control wiring ongoing. − Circuits being pulled to electrical panels in Area A. − Fire alarm wiring installation ongoing in area A. − Data, fire alarm, and security wiring being pulled continues. − Window and curtain wall installation continues. − Domestic water piping installation to water heaters ongoing.
First Floor Terrazzo Finishing
Mechanical Mezzanine Control Panels
Piping Water Heaters
P a g e | 5
− Roof soffit and fascia installation continues. − Fascia gutter and downspout installation ongoing.
Mechanical Mezzanine
Installation of Wet Bed in Kitchen
Boiler Start Up
Quarry Tile Installation in Kitchen
Area C Mezzanine Ductwork
P a g e | 6
Building Feature Highlight The Crooked Billet site slopes from front to back. To take advantage of the topography and in lieu of adding more stone fill on the site, a District-wide storage room was incorporated into the school design. The space can be accessed
from both inside and out and is equipped with fire suppression, security, and data systems. CROOKED BILLET ELEMENTARY
Gym Floor Prep for Wood Flooring
Gym Scoreboard Placement
P a g e | 7
SGA Rendering of Area A
2/29/20 Status of Area A
P a g e | 8
Aerial view of Site
Aerial view of Area B and C
P a g e | 9
Building Layout:
AREA C
AREA A
AREA B
P a g e | 10
Made with FlippingBook Publishing Software